My Lords, I think that they should have notice, but the point is that the paragraph 17 conditions exclude activities that would impose an additional burden on a site provider, as I have just said, and activities that disrupted their day-to-day business or create new health and safety risks would not satisfy the requirement. I honestly think that answers the point.
I think that I have answered most of the questions; I will obviously check Hansard and, if I have not, I will come back. In the meantime, I hope that the noble Lord, Lord Bassam, is prepared to withdraw this amendment.
I move on to Clause 66, as probed by my noble friend, Lady McIntosh of Pickering, with the support of the noble Earl, Lord Devon. It creates a bespoke process for the court to impose an agreement where an operator needs a person, to whom I shall refer as “the landowner”, to confer or be bound by code rights and that person fails to respond to repeated requests for such rights.
The provisions require an operator to have sent an initial request notice and two warning notices, followed by a final notice, to the landowner. There must be a period of 14 days between the giving of each notice,
meaning that the landowner will have been given a minimum of 56 days in which to respond to the operator. For the landowner to fall out of scope of Part 4ZA, all that is required of them is to respond to any of the above notices in writing before the operator applies to the court. If granted, a Part 4ZA order will impose an agreement on the landowner and operator. The terms of that agreement are to be specified in regulations made following stakeholder consultation.
My noble friend asked about situations where landowners are non-responsive. If they are unwilling to engage, for example, in alternative dispute resolution processes, it will remain open to the operator to apply to a court under Part 4 of the code to seek an order to impose an agreement granting code rights. These provisions impose a six-year maximum time limit on the period for which rights conferred under a Part 4ZA order may last. I emphasise this detail because it forms an important part of the Bill’s safeguards on landowners’ property rights. This clause provides a much-needed process that will play a large part in ensuring that homes and businesses benefit from the national gigabit broadband upgrade and are not left behind. I therefore commend Clause 66.