High Speed Rail (West Midlands-Crewe) Bill

My Lords, I thank the noble Lords, Lord Berkeley and Lord Tunnicliffe, for their amendments in this group. They have been grouped together as they cover the very important areas of transparency and accountability. The Government agree that these areas are absolutely vital; we must ensure that the project is successful, and transparency and accountability will be at the heart of that. Like the noble Lord, Lord Adonis, I believe that HS2 must always strive to do better. That is good practice for all organisations.

That is why the Government have committed to providing an update to Parliament every six months on the progress of HS2. The first update was provided on 13 October, as has been noted, and that report covers data reported by HS2 Ltd to the end of August 2020. A copy of the report has been placed in the Libraries of both Houses. Furthermore, HS2 Ltd provides detailed annual reports to Parliament, as required by the DfT/HS2 Ltd framework document. Noble Lords will be aware that as principal accounting officer, the Permanent Secretary of the Department for Transport is accountable to Parliament for capital contributions and resources provided by HS2. The noble Lord, Lord Berkeley, referred to a recent letter from the Public Accounts Committee to the Permanent Secretary setting out a number of requests and observations, and this is a prime example of holding the Government and HS2 to account.

Specifically on environmental matters, if it is felt that a contractor is not meeting the requirements of the environmental minimum requirements, there is a three-step process that can be followed. In the first instance, the issue can be reported to the nominated undertaker, which in this case would be HS2. Secondly, if the issue is not resolved satisfactorily, it can be escalated and reported to my department, which can direct HS2 to implement corrective action. Finally, the issue can be reported to Parliament: to the Speaker in the House of Commons or to the Chairman of Committees in the House of Lords. Furthermore, individuals and bodies can raise issues with Sir Mark Worthington OBE, who is the independent construction commissioner for both phase 1 and phase 2a. This ensures access to clear, impartial advice and enables strong scrutiny of the project.

I turn to the issue of ancient woodlands. I understand and I commend the interest taken in our invaluable ancient woodlands and veteran trees. In the development of the project, every effort has been made to avoid or reduce the impact on ancient woodlands. For example, following extensive engagement with the Woodland Trust, we were able to offer a number of assurances in relation to ancient woodlands and veteran trees. Those include the retention of Noddy’s Oak near Stockwell Heath in Staffordshire, along with five other veteran trees.

I welcome the comments of the noble Lord, Lord Liddle, because we believe that we have a productive relationship with the Woodland Trust and we want very much for that relationship to continue. There are some places where we have not been able to protect a veteran tree or a piece of ancient woodland, and of course this is regrettable. However, HS2 is putting in place all possible mitigations to safeguard our environment as a whole. The environmental statements already report the likely significant effects of the phase 2a scheme on trees and woodland habitats, including veteran trees and ancient woodland. They also set out the proposed mitigations and compensations for the likely effects of the railway. HS2 has published an ancient woodland strategy for the scheme that sets out the expected loss of ancient woodland habitat and the range of compensation measures being proposed in response to those losses.

I know that there are concerns about how contractors can be held to account in undertaking works in or near ancient woodlands. As I have outlined previously, if it is felt that a contractor undertaking works authorised by the Bill is not meeting the environmental minimum requirements, there are steps that can be taken to ensure that there is an investigation. If any corrective action is needed, it is taken, and ultimately these steps can include a report to Parliament.

The Department for Transport and HS2 have done extensive work to assess, document and publicise the impact of the proposed scheme on the ecology of our beautiful urban and rural landscapes. A number of noble Lords have gone into detail about veteran trees and ancient woodlands, along with the broader environmental impacts of HS2. I will write to them in more detail on this because there is a fair amount to cover on the no net loss commitment of HS2, along with other things that can be done in order to achieve some net gain. I will also add some information on costs. Unfortunately, I do not fully recognise the costs that were put forward by my noble friend Lord Blencathra. I am not entirely sure where they came from, so I will set those out in more detail. I will also add some information about the nature and timing of the various reports. I realise that quite a number of reports have been produced and that it would be helpful for all noble Lords to understand where we are. There will certainly be more on the environmental matters when the Government’s response to the report of the Select Committee is published, which will happen shortly before Report. Also, in relation to this, I will arrange a meeting for noble Lords, probably with the Minister for HS2, so that we can go into these matters in more detail.

I believe that the current level of reporting across the project, which has only very recently been revised, is proportionate and sufficient. It comes alongside increased oversight of the project by not only my colleague Andrew Stephenson, the HS2 Minister, but the ministerial task force chaired by the Transport Secretary, which includes ministerial colleagues from across government. Both these measures are relatively new. They need time to bed in and for the impact to be felt. I therefore invite the noble Lord, Lord Berkeley, to withdraw his amendment.

About this proceeding contribution

Reference

807 cc384-6GC 

Session

2019-21

Chamber / Committee

House of Lords Grand Committee
Back to top