High Speed Rail (West Midlands-Crewe) Bill

My Lords, in general, we view the amendment favourably. It seems to have two points to it. The first is to try to secure some continuity, as spelled out by the noble Baroness, Lady Randerson. The concept of continuity in railway construction is a sound one. Unfortunately, it is a sound principle that we tend not to keep to. The key part of the amendment seems to be the question of whether Her Majesty’s Government will commit to building HS2 phase 2b to Leeds in full. For the avoidance of doubt, Labour’s answer is that we fully support the HS2 concept and the concept that phase 2b should be built to Leeds in full.

I think we already know what the Minister will say. Andrew Stephenson was asked this question in the other place on 22 October. He said that

“when the Prime Minister gave the go-ahead to HS2 in February this year, he said that we were committed to delivering phase 2b but how phase 2b was delivered would be subject to the integrated rail plan. We have been making significant progress with the integrated rail plan. Sir John Armitt and the National Infrastructure Commission have already published their interim report. We look forward to their further recommendations and to responding to them before Christmas.”—[Official Report, Commons, 22/10/20; col. 1213.]

That caused me to look up the interim report, since it seems central to how the question posed in the amendment will be answered. When I found it and skimmed through it, I came up with two questions. The first is very simple: when will the final report on this issue be published? The interim report promises that it will be published in November. It should be noted that Andrew Stephenson said that it would be published by Christmas. If it were published in November, it might be available before we get to Report, which would be extremely useful. When does the Minister expect the report to be published and when does she expect the Government’s response?

The other perhaps disturbing feature of the interim report is the commitment to a very different methodology from that used in the past. Essentially, what is said about a plan depends on the methodology and assumptions in the analysis that answers the question, to what extent and to what standard should the railway be built? Can the Minister assure the Committee that the methodology and assumptions will produce an answer no less favourable to the Leeds branch than those used in HS2? Put another way, if the criteria used in the original HS2 decision would say yes to Leeds but the new criteria say no, surely, this cannot be levelling up. I have seen precious few examples of levelling up, and a failure to build HS2 phase 2b to Leeds—indeed, a failure to build HS2 in full—surely is a statement that the commitment to levelling up is meaningless.