My Lords, I thank my noble friend Lord Moylan for tabling Amendment 284. I shall not be commenting on any individual planning case at all. Obviously it would not be correct for me to do so.

Amendment 284 seeks to ensure that the progress of applications, in circumstances where a Section 35 direction has been made, is monitored and kept under review by the Secretary of State. I agree that developments, especially nationally significant infrastructure projects, should enter our planning system efficiently, and doing so is crucial for ensuring that local communities and businesses can express their views on the real impacts that these projects can have on them.

The NSIP consenting process has served the UK well for more than a decade for major infrastructure projects in the fields of energy, transport, water, waste and wastewater, and has allowed these projects to be consented within an average of around four years. Some of these projects enter the NSIP planning system under a Section 35 direction. This is the beginning of the planning process for some projects and offers prospective applicants certainty that they can take their projects through the NSIP consenting process. This consenting

mechanism has been used successfully by 18 developers and allowed them to capitalise on the benefits that the NSIP regime offers.

Very occasionally, applications for development consent can be delayed or even withdrawn. This applies to applications that either automatically qualify as an NSIP under Part 3 of the Planning Act or are directed in through Section 35. This often occurs to allow developers time to ensure that applications entering the system are of the standard needed to efficiently and robustly undergo the scrutiny required. I acknowledge that this can translate into uncertainty for some communities, businesses and investors that have the potential to be affected by such projects.

Under Section 233(2) of the Planning Act, the Secretary of State already has the power to revoke a direction to treat a project as an NSIP, and thus no longer allow the project in question to enter the NSIP planning system through these means. The Secretary of State may consider using this power, for example, if it becomes clear that the rationale or basis on which the Section 35 direction was made has changed, so this is no longer the correct and appropriate consenting option for the project in question. I appreciate why my noble friend has raised this amendment, and I hope he will withdraw it following the reassurances I have provided.

The noble Lord, Lord Stunell, and others brought up the interesting issue of oversight. We are currently working to set this up. Minister Rowley is setting up an IMG which will look at the cross-cutting issues on projects, but he cannot get involved in the specifics on projects, in order not to prejudice, obviously, future decision-making, particularly as a Planning Minister. I will also take on board the issue that the noble Baroness, Lady Hayman of Ullock, brings up about the capacity within local planning authorities to deal with these very big projects. I think it is something we can feed back in and I will do so.