15: Schedule 1, page 29, line 25, at end insert—

“(5) The scheduled works may not commence until the Secretary of State has published a report considering the impact of road traffic resulting from the works.

(6) The report must include—

(a) an assessment of estimated levels of road traffic resulting from the works;

(b) an assessment of the conditions of any roads which may experience an increase in traffic as a result of the works;

(c) results from a consultation of residents and local authorities likely to be impacted in each Parish in which the works take place.”