My Lords, we come to a substantial group containing Amendments 5, 6, 7 and 9 in my name, and Amendments 15, 16 and 17 in the name of the noble Baroness, Lady Pinnock.
Amendment 5 seeks to make progress in respect of the recommendations of the first phase of the Grenfell Tower inquiry. It is disappointing that progress has been so slow, frankly, on all these matters following the tragedy at Grenfell Tower on 14 June 2017, some 40 months ago. We have on record pledges from Ministers to implement in full the recommendations in the report of the first phase of the inquiry, but the Bill before us today does not include any of the provisions or measures called for in the inquiry to be implemented. When the Bill was before the other place, the Government did not take the opportunity afforded to them to correct this. They opposed moving forward and instead said that they would launch a consultation. The consultation was launched in July and ends this month, a full year after they pledged to implement the recommendations of the inquiry.
I hope the Minister can set out for the House the timescale the Government are working to, as people have waited far too long for legislative action. Will he say why the Government are not even prepared to include the simplest of the recommendations the inquiry called for in this Bill—recommendations such as the inspection of fire doors and the testing of lifts? There is an urgent need for these recommendations to be implemented and the Government need to act with much more speed.
Amendment 6 returns to points I made previously today and at Second Reading. The fire safety Order requires regular fire risk assessments in buildings, but there is no legal requirement for those conducting these assessments to have any form of training or accreditation for this work. Although this service can be commissioned from council-run building control services, numerous private providers compete for the work and their numbers have rapidly expanded since the fire at Grenfell Tower. Numerous experts have criticised the poor quality of the work in building control and fire safety. As I have said before, we do not want a race to the bottom, where anybody can set up and say they are an inspector with very little training to do the work.
I want to hear from the Minister today that we will ensure that when fire assessments are done, we will have people who are properly accredited and able to do the work. Although I accept that there are some voluntary accreditation schemes, it is sadly the case that the use of unregistered fire inspectors is commonplace. The lack of training and accreditation in this important area of work is, frankly, unacceptable. The Government should be using this Bill to legislate for higher standards and greater public accountability in fire inspections.
Amendment 7 requires the schedule for inspecting buildings containing two or more sets of domestic premises to be based on a prioritisation of risk. At present, there is no guarantee that the schedule for inspections will be based on any sort of risk analysis rather than an arbitrary distinction between types of buildings. This was raised in the Commons by my honourable friend the Member for Croydon Central, who said that many experts and stakeholders have “significant concerns” over how the Bill would be implemented. She drew attention to reference by the Minister in Committee to:
“The building risk review programme, which will … ensure that local resources are targeted at those buildings most at risk”.—[Official Report, Commons, Fire Safety Bill Committee, 25/6/20; col. 62.]
I agree, but it should also be pointed out that local fire and rescue services know their area well, and know the buildings where there is greatest risk. It should be they who decide the priority list.
Amendment 9 would require the UK Government, for England, and the Welsh Government, for Wales, to specify when a waking watch must be in place for buildings that contain two or more sets of domestic premises and have fire safety failures. There are still major issues around removal of flammable ACM cladding from tower blocks. A significant number of buildings remain covered, more than three years after the Grenfell
Tower fire, and other types of dangerous cladding have also been identified and not yet removed from buildings.
I accept that coronavirus caused many contractors to stop work on cladding sites, while others have not even begun work because of legal disputes, including, as I mentioned in a previous debate, disputes over guarantees and insurance payments. These delays mean that residents are in buildings that are unsafe, which cannot be right, or face extortionate fees for removal. Guidance from the National Fire Chiefs Council suggests waking watches should be a temporary measure, yet some residents have been forced to pay for waking watches for years, with some put in place immediately after the fire at Grenfell Tower, more than 40 months ago. They can cost up to £10,000 a week.
Amendments 15, 16 and 17 have considerable merit. I am happy to offer my support to the noble Baroness, Lady Pinnock, and will listen carefully to her when she speaks to them. I hope the Minister will give a full response to all the amendments and I beg to move.