The amendments we have received from the other place make a number of changes to the Bill. In most instances, as the Minister mentioned, those relate to the commencement of the closure of the RO. That is essentially because of the Bill’s progress through Parliament and the potential charge of retrospectivity against the Bill. It is good that the issue has been rectified, and that the Government have confirmed that they do not intend to backdate the closure of the RO.
However, those changes point to the issue raised in amendment 7T, with which the Government have a motion to disagree. We need to be clear that the amendment is not saying that changing the closure date for the RO for onshore wind is wrong, although I continue to contend that it is. Contrary to the impression the Minister has given this afternoon, developers of projects did not realise that the closure date would be earlier than previously thought. Indeed, the so-called warnings before the general election, which she mentioned, were not about the early closure of the RO, but about future funding for onshore wind in general. Developers of projects knew that the RO would come to an end in March 2017, and many had spent several years—a long period—in the development process before the warnings were issued, and before the policy was put forward in the manifesto and, subsequently, the Bill. Having planned on the basis of the notion that the RO would come to
an end, they found out very late in the day that the goalposts had been arbitrarily moved, and that their investment was lost overnight as a result.
Nor is the amendment in any way contrary to manifesto commitments; it is not about the principle of the early closure of the RO, but about the grace periods that follow from that closure process. It is not saying that there should not be grace period exceptions for schemes that, for various reasons, might fall foul of the new, arbitrary cut-off date. By highlighting a small number of projects that have fallen foul of the cut-off date for very specific reasons, it is saying that grace-period schemes should be built on a reasonable level of equity and fairness, and should work within an understanding of proper reasons for exemption; they should not simply impose a few extended, but nevertheless still arbitrary, cut-off dates for projects.
Lords amendment 7T highlights a particularly egregious inequity in the grace-period scheme. This involves schemes that have, even according to the new guidelines laid down in the Bill process, done the right thing throughout by seeking and securing local support. As the Government said earlier in the passage of the Bill, it was to be the sine qua non of permission for the development of any onshore wind in the future that local communities should have the final say in decisions; schemes, it was said, should obtain support, perhaps through local planning approval, and should not, for example, seek to win an appeal on the basis of national determination, having been turned down at local level.
The schemes covered by the amendment fit exactly that description. They have determinedly gone through the local process and engaged with it, rather than standing back and waiting to progress through an appeal. They have won local community support, in each instance through the granting of a planning decision by the local authority. The only issue is that, having gone through that often lengthy process of local consultation, they find that the successful, locally supported outcome has, at the stroke of a pen, effectively been turned into refusal. That has happened because the final planning certificate has not arrived by the cut-off date because of issues relating not to the permission, but to details of section 106 agreements on community benefit or similar issues, or to section 75 agreements in Scotland—that is, issues that arise not as part of the agreement process, but because the agreement has been reached. As these schemes could not produce a final, formal planning certificate by the arbitrary date of 18 June, the scheme as a whole was lost.
Here is the timetable of one such scheme, the Twentyshilling Hill wind farm in Dumfriesshire. The planning application was initially made on 15 March 2013 —a long time ago. It was approved by a planning committee, subject to a section 75 agreement, on 16 December 2014. It was not the fault of the wind farm applicant that the council took a few months to settle the section 75 application. Even so, the application was agreed on 17 June—again, before the cut-off date. However, despite the agreement being public and on the council website, the final certificate did not arrive until 1 July, making it null and void in the Government’s eyes, as the Minister has stated.
In retrospect, it might have been wiser for those and other developers not to take too much time on, or give too much attention to, local agreement, but to instead
precipitate an appeal that they might have won. Indeed, when developers have done just that and the appeal decision has arrived after the cut-off date of 18 June 2015—we heard of such instances during the passage of the Bill—it has been accepted because of a provision relating to the grace period. The projects are deemed to have been okay all along and are allowed to proceed. That is frankly perverse, and it falls seriously short of the test of reasonableness and equity that ought to inform any grace period arrangement.
Lords amendment 7T relates to a small number of cases and seeks to restore a semblance of equity to the process. It is based on the principle that the Government themselves promoted as the basis for decisions on onshore wind applications. It is a principle for the future that, incidentally, Labour supports.
I shall explain the equity. If a local planning committee found in favour of a planning decision before 18 June, and the decision was arrived at via a process of consultation and community acceptance of the application, it should be covered by the grace period provisions. This small amendment would affect only about half a dozen schemes. In the overall scheme of things, it would make an insignificant inroad into levy control framework financial provisions, as far as the RO is concerned. It would, however, place a much-needed patch of equity on the grace period structure, and perhaps point the way to addressing seriously a future issue. That issue is this: are the Government intent on ensuring that onshore wind will be built in the future—it is, after all, the cheapest and most cost-effective renewable available—if local communities support the proposals, or do they intend to use national clout to override local wishes in pursuit of an overall closure of onshore wind, at least in England?
Accepting the amendment and finalising the Bill in this way would go a long way to restoring a principle that was supposedly central to the process for the future, and it would demonstrate to local communities that they really will be able to decide and not have their local wishes snuffed out by a fiat from the centre.