UK Parliament / Open data

Energy Bill

Proceeding contribution from Michael Fallon (Conservative) in the House of Commons on Monday, 3 June 2013. It occurred during Debate on bills on Energy Bill.

I should be happy to check that. I suspect that the hon. Gentleman may be right, but I think that some of my objections would still apply. These things change over time, and I should prefer to have them in secondary legislation. However, if I have wrongly suggested that this is a novel approach, I will certainly get back to the hon. Gentleman.

On amendment 94, we need to be sure that independent generators have a fair chance of entering the market. I am sure that my hon. Friend the Member for Rochester and Strood (Mark Reckless), and other Members who have signed his amendment, would support that. Ofgem will shortly be releasing details of its proposed reforms to improve market liquidity, and I welcome that progress. However, it is crucial for the Government to be able to act if Ofgem is unable to deliver ambitious reforms allowing more independent generation in a timely fashion. That is why we need the backstop powers in clause 38.

Amendments 95 to 99, also tabled by the my hon. Friend the Member for Rochester and Strood, would remove the emissions performance standard from the Bill. I know that my hon. Friend is concerned about its impact on coal-fired generation, and suspect that he feels that the carbon price floor provides sufficient market signals to disincentivise such generation, but the Government's objective is to deliver a clear and unambiguous message to investors that coal-fired generation must significantly reduce its emissions to have a long-term role in our energy mix.

The commitment to decarbonisation is delivered through economic signals such as support for the carbon price, through planning policy—which states that new coal-fired

power stations should be equipped with carbon capture and storage—and through the EPS, a coalition commitment that places a firm limit on the amount of carbon that can be emitted, regardless of the price of coal or carbon. That commitment to reducing emissions would be undermined by amendments 173 to 175, and I hope that my hon. Friend the Member for Daventry understands why I cannot accept them. In relation to amendment 174, I should point out that the formula in clause 42 was carefully designed to ensure that potential emissions from new coal plant would be at least halved.

Amendment 148, tabled by the hon. Member for Brent North, would apply the EPS to existing coal-fired plant that installed pollution abatement equipment to comply with the industrial emissions directive. I understand his fear that, if the relatively low price of coal continues, it may lead to levels of coal generation that will put our decarbonisation objectives at risk. However, our electricity market reform measures should mitigate the risk of carbon “lock-in” by driving investment in new low-carbon generation which will increasingly displace generation from fossil fuel.

Amendment 150 would reduce by 15 years the period in which the emissions limit for a new plant is “grandfathered”. Grandfathering until 2045 gives investors in new gas plant the regulatory certainty they need that the EPS will not stop them from making a return on their investment, thus assisting the provision of the new plants that we require in order to replace ageing capacity. Let me be clear: we need gas-fired generation in our future energy mix to balance increasing levels of intermittent and inflexible plant coming on to the system. Amendment 150 would deter such investment and thus reduce, not increase, the reliability of our electricity supplies.

5.30 pm

Lastly on the EPS, Opposition Members have tabled amendment 179, which seeks to exempt CCS projects from the EPS during their commissioning period. The House will recall that the draft Bill contained a similar exemption, but was removed following recommendations from the Select Committee on Energy and Climate Change.

Our view is that the best way to manage risks to CCS projects from the EPS is through each project’s funding contract. That provides greater flexibility to manage project risks in one place and on a case-by-case basis. Also, the EPS already provides a degree of flexibility for plant during the commissioning period.

About this proceeding contribution

Reference

563 cc1275-6 

Session

2013-14

Chamber / Committee

House of Commons chamber
Back to top